Bidfident

Bidfident for custom home builders

Estimating software for new homes

Custom homes make for long estimates with a lot to keep track of. Bidfident prices the framing package, shingles, insulation and drywall by the square foot, from your own rates for carpenters, drywallers and labourers, with trim as a lump sum. Mechanical and electrical bids sit side by side, supervision and temporary power follow the build schedule, and a finished basement can stay on the sheet as an alternate.

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.

Sound familiar?

  • A house too long to see on one screen

    Hundreds of rows, and the only way to see the whole house is to scroll. In Bidfident you group the sheet by division or by floor, then collapse it to see every subtotal at once.

  • Six months of site costs to keep up to date

    Supervision, temporary power and the toilet are priced for 26 weeks, then the build runs four weeks longer. In Bidfident weekly and monthly items follow the job duration.

  • Last year's rates in this year's house

    The new estimate is a copy of the last one, with last year's rates still in it. In Bidfident every estimate uses the company's one rate library, and a submitted bid keeps the rates it was priced with.

How Bidfident fits your work

  • Bidfident screenshot: the whole house, division by division

    The whole house, division by division

    Group the sheet by CSI division, from framing and roofing to insulation, drywall and finish carpentry, each with its subtotal. Collapse it to see the whole house.

  • Bidfident screenshot: every trade at its own rate

    Every trade at its own rate

    Carpenters, drywallers and labourers, each at their rate from the company library. Change a rate once and every line using it updates.

  • Bidfident screenshot: mechanical and electrical bids side by side

    Mechanical and electrical bids side by side

    Enter each bid for plumbing, heating and ventilation, and for electrical. The lowest is flagged and carried unless you pick another, and a declined bid is ignored.

  • Bidfident screenshot: site costs for the length of the build

    Site costs for the length of the build

    Supervision by the week, temporary power and toilet by the month, linked to the job duration. Change the weeks and they follow.

  • Bidfident screenshot: totals by cost code

    Totals by cost code

    The cost report totals the house by cost code, under each division with its subtotal. Click a row to jump to it, or copy the report as CSV.

  • Bidfident screenshot: from cost to bid, to the cent

    From cost to bid, to the cent

    Direct cost, then contingency and fee, with insurance on the subtotal after fee, then GST shown separately. The basement alternate is shown for reference only.

Worked example: a 2,400 sf custom home

A made-up job, priced in Bidfident: 26 lines of your own work, 4 subtrades and 6 overhead items over a 26-week job. The 6 lines this page talks about are listed one by one, and the rest are added up in one row. It's the same job you can open as an example project in Bidfident, so every figure below matches it.

To open this job in Bidfident: sign in and set up your company in Canada, then on the Projects screen, under Example project, pick "Renovation and home builders" and "New homes" and press Add example project.

Your own work
ItemAmount
Framing package, walls, floors and roof, 2,400 sf
  • Labour: 2,400 sf × 0.28 hrs = 672 hrs at $78.00/hr (framing carpenter) = $52,416.00
  • Material: 2,400 sf × $24.00 + 8% waste = $62,208.00
$114,624.00
Asphalt shingles with underlayment, 2,900 sf
  • Labour: 2,900 sf × 0.03 hrs = 87 hrs at $78.00/hr (framing carpenter) = $6,786.00
  • Material: 2,900 sf × $2.60 + 10% waste = $8,294.00
$15,080.00
Insulation and vapour barrier, 5,200 sf
  • Labour: 5,200 sf × 0.012 hrs = 62.4 hrs at $55.00/hr (general labourer) = $3,432.00
  • Material: 5,200 sf × $1.35 + 5% waste = $7,371.00
$10,803.00
Drywall, taped and sanded, 8,600 sf
  • Labour: 8,600 sf × 0.02 hrs = 172 hrs at $72.00/hr (drywall installer) = $12,384.00
  • Material: 8,600 sf × $0.85 + 10% waste = $8,041.00
$20,425.00
Interior doors and trim, 1 LS
  • Labour: 1 LS × 160 hrs = 160 hrs at $78.00/hr (framing carpenter) = $12,480.00
  • Material: 1 LS × $14,500.00 = $14,500.00
$26,980.00
Alternate 1: finished basement, 1,100 sf
  • Labour: 1,100 sf × 0.18 hrs = 198 hrs at $78.00/hr (framing carpenter) = $15,444.00
  • Material: 1,100 sf × $22.00 = $24,200.00
  • Excluded: priced and kept on the estimate, but not in any total
$39,644.00
21 more lines of your own work
  • Labour $57,973.70 + material $76,589.60 + equipment $4,298.00
$138,861.30
Subtrades
ItemAmount
Plumbing, heating and ventilation
  • Bids: Bidder A $46,500.00, Bidder B $43,900.00
  • Carrying the lowest: Bidder B
$43,900.00
Electrical
  • Bids: Bidder A $28,400.00, Bidder B $29,600.00, Bidder C $27,250.00
  • Carrying the lowest: Bidder C
$27,250.00
Foundation, footings, walls and slab
  • Bids: Bidder A $38,500.00, Bidder B $41,200.00
  • Carrying the lowest: Bidder A
$38,500.00
Owner selections: cabinets, countertops and flooring, allowance
  • No bids yet: carrying the plug amount
$68,000.00
Overhead
ItemAmount
Site supervision, part-time
  • 26 wk × $650.00, following the job duration
$16,900.00
Temporary power and toilet
  • 26 weeks × $480.00 a month × 12 ÷ 52, following the job duration
$2,880.00
Waste bins, emptied
  • 10 ea × $550.00
$5,500.00
Building permit, inspections and new home warranty
  • 1 LS × $6,850.00
$6,850.00
Survey stakeout and real property report
  • 1 LS × $1,850.00
$1,850.00
Final cleaning
  • 1 LS × $1,450.00
$1,450.00
Bid summary
ItemAmount
Own work
  • Labour $145,471.70 + material $177,003.60 + equipment $4,298.00
$326,773.30
Excluded lines, not counted$39,644.00
Subtrades$177,650.00
Overhead
  • 26 weeks
$35,430.00
Direct cost
  • Own work + subtrades + overhead
$539,853.30
Contingency
  • 4% of direct cost
$21,594.13
Fee
  • 12% of direct cost plus contingency
$67,373.69
Subtotal before bonding$628,821.12
Bonding
  • 0% of the subtotal
$0.00
Insurance
  • 0.5% of the subtotal
$3,144.11
Bid total
  • The price you submit, before GST
$631,965.23
GST, for reference
  • 5%, shown separately and not part of the bid total
$31,598.26

See it in Bidfident

Labour by trade Framing, drywall and insulation lines each take their trade's rate from your company's library. 33 sec
Site costs that follow the schedule Supervision and temporary power follow the build's duration. Change the weeks and they update. 38 sec
Version history Compare the house as it was priced before the plans were revised with now, and restore the old version with a click. 35 sec

Coming soon Ask your estimate anything. Claude first, ChatGPT to follow. See how it will work

Questions

Can I collapse the estimate to see the whole house?

Yes. Group the sheet by CSI division, area or location, then collapse the groups to see every subtotal on one screen.

Will last year's house bids change when I raise my carpenter and drywaller rates?

No, not once a bid is submitted. A submitted bid keeps the labour and equipment rates it was priced with.

Can I go back to the house as it was before the plans were revised?

Yes. Bidfident saves as you go. Compare any saved version of the house with now, and restore it with a click.

Can temporary power be priced by the month?

Yes. Site costs can be by the week, month, lump sum or each, and weekly and monthly items can follow the job duration.

Does the bid for a new home show GST or HST?

Yes. In Company settings, name your tax (HST, for example) and set its rate. The bid summary shows it on one line, for reference, and the bid total is before tax.

Can I track actual costs against the estimate during the build?

No. Bidfident is for pricing the job, not job costing. You can copy the cost report as CSV for your own spreadsheet.

Does Bidfident work with Claude or ChatGPT?

Not yet, but it's coming. You'll be able to connect Bidfident to your own Claude or ChatGPT account and ask about your estimates in plain English. The answers will come from Bidfident's own figures, so they match the estimate. It will use the account you already have: Claude first, ChatGPT to follow.

Price your next new home in Bidfident

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.