Bidfident

Bidfident for housebuilders

Estimating software for new builds and one-off homes

One-off new builds make for long estimates. Bidfident prices the timber frame kit, roof covering, insulation and plasterboard by the square metre, from your own rates for carpenters, dryliners and labourers, with internal joinery as a single item. Mechanical and electrical quotes sit side by side, supervision and temporary electrics follow the programme, and fitting out the basement can stay on the sheet as an option.

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.

Sound familiar?

  • A house too long to see on one screen

    Hundreds of rows, and the only way to see the whole house is to scroll. In Bidfident you group the sheet by division or by floor, then collapse it to see every subtotal at once.

  • Six months of prelims to keep up to date

    Supervision, temporary electrics and the site toilet are priced for 26 weeks, then the build runs four weeks over. In Bidfident weekly and monthly items follow the job duration.

  • Last year's rates in this year's house

    The new estimate is a copy of the last one, with last year's rates still in it. In Bidfident every estimate uses the company's one rate library, and a submitted tender keeps the rates it was priced with.

How Bidfident fits your work

  • Bidfident screenshot: the whole house, division by division

    The whole house, division by division

    Group the sheet by division, from frame and roof to insulation, plasterboard and second fix joinery, each with its subtotal. Collapse it to see the whole house.

  • Bidfident screenshot: every trade at its own rate

    Every trade at its own rate

    Carpenters, dryliners and labourers, each at their rate from the company library. Change a rate once and every line using it updates.

  • Bidfident screenshot: mechanical and electrical quotes side by side

    Mechanical and electrical quotes side by side

    Enter each quote for plumbing, heating and ventilation, and for the electrical installation. The lowest is flagged and carried unless you pick another, and a declined quote is ignored.

  • Bidfident screenshot: prelims for the length of the build

    Prelims for the length of the build

    The site manager by the week, temporary electrics and the site toilet by the month, linked to the job duration. Change the weeks and they follow.

  • Bidfident screenshot: totals by cost code

    Totals by cost code

    The cost report totals the house by cost code, under each division with its subtotal. Click a row to jump to it, or copy the report as CSV.

  • Bidfident screenshot: from cost to tender total, to the penny

    From cost to tender total, to the penny

    Direct cost, then contingency and fee, with insurance on the subtotal after fee, then VAT shown separately for reference. The basement option is shown for reference only.

Worked example: a 223 m² one-off new build

A made-up job, priced in Bidfident: 26 lines of your own work, 4 subcontract packages and 6 preliminaries items over a 26-week programme. The 6 lines this page talks about are listed one by one, and the rest are added up in one row. It's the same job you can open as an example project in Bidfident, so every figure below matches it.

To open this job in Bidfident: sign in and set up your company in the UK, then on the Projects screen, under Example project, pick "Refurbishment and housebuilders" and "New builds" and press Add example project.

Your own work
ItemAmount
Timber frame kit, walls, floors and roof, 223 m2
  • Labour: 223 m2 × 3 hrs = 669 hrs at £30.00/hr (carpenter) = £20,070.00
  • Materials: 223 m2 × £275.00 + 8% waste = £66,231.00
£86,301.00
Concrete interlocking roof tiles, battens and underlay, 270 m2
  • Labour: 270 m2 × 0.32 hrs = 86.4 hrs at £30.00/hr (carpenter) = £2,592.00
  • Materials: 270 m2 × £26.00 + 10% waste = £7,722.00
£10,314.00
Insulation and vapour control layer, 483 m2
  • Labour: 483 m2 × 0.13 hrs = 62.79 hrs at £22.00/hr (labourer) = £1,381.38
  • Materials: 483 m2 × £12.00 + 5% waste = £6,085.80
£7,467.18
Plasterboard, taped and jointed, 800 m2
  • Labour: 800 m2 × 0.2 hrs = 160 hrs at £29.00/hr (dryliner) = £4,640.00
  • Materials: 800 m2 × £5.50 + 10% waste = £4,840.00
£9,480.00
Internal doors, architraves and skirting, 1 item
  • Labour: 1 item × 160 hrs = 160 hrs at £30.00/hr (carpenter) = £4,800.00
  • Materials: 1 item × £7,800.00 = £7,800.00
£12,600.00
Option 1: basement fitted out, 102 m2
  • Labour: 102 m2 × 1.95 hrs = 198.9 hrs at £30.00/hr (carpenter) = £5,967.00
  • Materials: 102 m2 × £260.00 = £26,520.00
  • Excluded: priced and kept on the estimate, but not in any total
£32,487.00
21 more lines of your own work
  • Labour £25,319.60 + materials £50,525.93 + plant £2,184.75
£78,030.28
Subcontractors
ItemAmount
Plumbing, heating and ventilation
  • Quotes: Bidder A £26,500.00, Bidder B £24,800.00
  • Carrying the lowest: Bidder B
£24,800.00
Electrical installation
  • Quotes: Bidder A £11,800.00, Bidder B £12,400.00, Bidder C £11,200.00
  • Carrying the lowest: Bidder C
£11,200.00
Foundations and ground-bearing slab
  • Quotes: Bidder A £21,180.00, Bidder B £22,660.00
  • Carrying the lowest: Bidder A
£21,180.00
Client choices: kitchen, worktops and flooring, allowance
  • No quotes yet: carrying an allowance
£32,000.00
Preliminaries
ItemAmount
Site manager, part-time
  • 26 wk × £450.00, following the programme
£11,700.00
Temporary electrics and site toilet
  • 26 weeks × £320.00 a month × 12 ÷ 52, following the programme
£1,920.00
Skips, exchanged
  • 10 ea × £330.00
£3,300.00
Building control and structural warranty fees
  • 1 LS × £3,200.00
£3,200.00
Setting out and as-built survey
  • 1 LS × £950.00
£950.00
Builders' clean
  • 1 LS × £650.00
£650.00
Tender summary
ItemAmount
Own work
  • Labour £58,802.98 + materials £143,204.73 + plant £2,184.75
£204,192.46
Excluded lines, not counted£32,487.00
Subcontractors£89,180.00
Preliminaries
  • 26 weeks
£21,720.00
Direct cost
  • Own work + subcontractors + preliminaries
£315,092.46
Contingency
  • 4% of direct cost
£12,603.70
Overheads and profit
  • 12% of direct cost plus contingency
£39,323.54
Subtotal before the bond£367,019.70
Bond
  • 0% of the subtotal
£0.00
Insurance
  • 0.5% of the subtotal
£1,835.10
Tender total
  • The price you tender, before VAT
£368,854.80
VAT, for reference
  • 20%, shown separately and not part of the tender total
£73,770.96

See it in Bidfident

Labour by trade Frame, plasterboard and insulation lines each take their trade's rate from your company's library. 33 sec
Site costs that follow the schedule Supervision and temporary electrics follow the build's duration. Change the weeks and they update. 38 sec
Version history Compare the house as it was priced before the drawings were revised with now, and restore the old version with a click. 35 sec

Coming soon Ask your estimate anything. Claude first, ChatGPT to follow. See how it will work

Questions

Can I collapse the estimate to see the whole house?

Yes. Group the sheet by division, area or location, then collapse the groups to see every subtotal on one screen.

Will last year's new build tenders change when I put up my carpenter and dryliner rates?

No, not once a tender is submitted. A submitted tender keeps the labour and plant rates it was priced with.

Can I go back to the house as it was before the drawings were revised?

Yes. Bidfident keeps a version each time it saves, and about every 10 minutes while it autosaves. Compare any saved version of the house with now, and restore it with a click.

Can temporary electrics be priced by the month?

Yes. Prelims can be by the week, month, lump sum or each, and weekly and monthly items can follow the job duration.

Does the tender for a new build show VAT?

Yes, at 20%, on its own line and for reference only. The tender total is before VAT, and the tax's name and rate can be changed in Company settings.

Can I track actual costs against the estimate during the build?

No. Bidfident is for pricing the job, not cost value reconciliation. You can copy the cost report as CSV for your own spreadsheet.

Does Bidfident work with Claude or ChatGPT?

Not yet, but it's coming. You'll be able to connect Bidfident to your own Claude or ChatGPT account and ask about your estimates in plain English. The answers will come from Bidfident's own figures, so they match the estimate. It will use the account you already have: Claude first, ChatGPT to follow.

Price your next new build in Bidfident

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.