Refurbishment work is priced room by room. In Bidfident you price soft strip, stud partitions and plasterboard by the square metre, kitchen units by the metre and doors by number, from your own joiner and labourer rates. Plumbing and electrical quotes sit side by side, skips and the lead joiner are carried as prelims, and options like underfloor heating stay on the sheet without counting.

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.

Sound familiar?

  • Every room in one long list

    The kitchen, the dining room and the downstairs WC all end up in one column of rows, and the client asks what the kitchen alone comes to. In Bidfident you tag each line with an area and group the sheet by it, with a subtotal for every room.

  • With and without the underfloor heating

    The client wants two prices, so the spreadsheet gets copied and the copies drift apart. In Bidfident the upgrade is switched off and stays on the sheet, struck through, with what it comes to shown beside the totals.

  • The joiner's rate typed on every row

    Rates get typed into each line, and when they go up some rows get missed. In Bidfident each line takes its trade's rate from the company library, so a joiner is a joiner on every line.

How Bidfident fits your work

  • Bidfident screenshot: room by room, with subtotals

    Room by room, with subtotals

    Tag each line with the kitchen, the dining room or the utility, and group the sheet by area. Each room gets its own subtotal, and you can collapse them to see the whole job.

  • Bidfident screenshot: upgrades the client can say yes to later

    Upgrades the client can say yes to later

    Underfloor heating, a boiling water tap or a better floor: price it as a line, then switch it off. It stays on the estimate, struck through, and isn't in the tender total.

  • Bidfident screenshot: joiners and labourers at their own rates

    Joiners and labourers at their own rates

    Soft strip by your labourers, partitions and kitchen fitting by your joiners, each line at its trade's rate from the library. Change a rate once and every line using it updates.

  • Bidfident screenshot: plumber and electrician quotes side by side

    Plumber and electrician quotes side by side

    Enter each quote for first and second fix, see the lowest flagged, and carry it or pick another. No quote yet? Carry an allowance until it comes in.

  • Bidfident screenshot: assemblies for the work you repeat

    Assemblies for the work you repeat

    A stud partition boarded both sides, a run of base units, a bathroom floor: save it once with its hours and materials, then fill a whole line with it on the next job.

  • Bidfident screenshot: square metres, metres and number

    Square metres, metres and number

    Plasterboard and flooring by the square metre, kitchen units by the metre, doors and sanitaryware by number. Waste goes on as a percentage, and the sheet works like Excel.

Worked example: kitchen and ground floor refurbishment in a 1960s bungalow

A made-up job, priced in Bidfident: 29 lines of your own work, 4 subcontract packages and 5 preliminaries items over a 6-week programme. The 6 lines this page talks about are listed one by one, and the rest are added up in one row. It's the same job you can open as an example project in Bidfident, so every figure below matches it.

To open this job in Bidfident: sign in and set up your company in the UK, then on the Projects screen, under Example project, pick "Refurbishment and housebuilders" and "Refurbishments" and press Add example project.

Your own work
ItemAmount
Soft strip and selective demolition, kitchen and dining room, 39 m2
  • Labour: 39 m2 × 0.85 hrs = 33.15 hrs at £22.00/hr (labourer) = £729.30
£729.30
Stud partition, 89 x 38 timber studs, boarded both sides, 17 m2
  • Labour: 17 m2 × 1.3 hrs = 22.1 hrs at £30.00/hr (joiner) = £663.00
  • Materials: 17 m2 × £24.00 + 8% waste = £440.64
£1,103.64
Plasterboard, taped, jointed and painted, 125 m2
  • Labour: 125 m2 × 0.3 hrs = 37.5 hrs at £30.00/hr (joiner) = £1,125.00
  • Materials: 125 m2 × £7.00 + 10% waste = £962.50
£2,087.50
Kitchen units, supplied and fitted, 8.5 m
  • Labour: 8.5 m × 6.5 hrs = 55.25 hrs at £30.00/hr (joiner) = £1,657.50
  • Materials: 8.5 m × £750.00 = £6,375.00
£8,032.50
Engineered oak flooring, 60 m2
  • Labour: 60 m2 × 0.55 hrs = 33 hrs at £30.00/hr (joiner) = £990.00
  • Materials: 60 m2 × £48.00 + 8% waste = £3,110.40
£4,100.40
Option 1: underfloor heating, kitchen, 22 m2
  • Labour: 22 m2 × 0.45 hrs = 9.9 hrs at £30.00/hr (joiner) = £297.00
  • Materials: 22 m2 × £75.00 = £1,650.00
  • Excluded: priced and kept on the estimate, but not in any total
£1,947.00
24 more lines of your own work
  • Labour £7,997.31 + materials £8,024.71 + plant £148.38
£16,170.40
Subcontractors
ItemAmount
Plumbing
  • Quotes: Bidder A £5,600.00, Bidder B £6,400.00
  • Carrying the lowest: Bidder A
£5,600.00
Electrical installation
  • Quotes: Bidder A £6,900.00, Bidder B £6,500.00, Bidder C £7,300.00
  • Carrying the lowest: Bidder B
£6,500.00
Quartz worktops, templated and fitted
  • Quotes: Bidder A £3,768.00, Bidder B £4,070.00
  • Carrying the chosen quote: Bidder B
£4,070.00
Asbestos survey, refurbishment, allowance
  • No quotes yet: carrying an allowance
£360.00
Preliminaries
ItemAmount
Site supervision, lead joiner
  • 6 wk × £450.00, following the programme
£2,700.00
Skips, exchanged
  • 4 ea × £330.00
£1,320.00
Dust sheets and protection upkeep
  • 6 wk × £79.80, following the programme
£478.80
Building control fees
  • 1 LS × £650.00
£650.00
Builders' clean
  • 1 LS × £280.00
£280.00
Tender summary
ItemAmount
Own work
  • Labour £13,162.11 + materials £18,913.25 + plant £148.38
£32,223.74
Excluded lines, not counted£1,947.00
Subcontractors£16,530.00
Preliminaries
  • 6 weeks
£5,428.80
Direct cost
  • Own work + subcontractors + preliminaries
£54,182.54
Contingency
  • 8% of direct cost
£4,334.60
Overheads and profit
  • 15% of direct cost plus contingency
£8,777.57
Subtotal before the bond£67,294.71
Bond
  • 0% of the subtotal
£0.00
Insurance
  • 0.5% of the subtotal
£336.47
Tender total
  • The price you tender, before VAT
£67,631.18
VAT, for reference
  • 20%, shown separately and not part of the tender total
£13,526.24

See it in Bidfident

Group by area or floor Tag lines by room and group the sheet, with a subtotal for the kitchen, the bathroom and the rest. 34 sec
Alternates, kept but not counted The underfloor heating stays on the estimate, struck through, with what it comes to shown beside the totals. 31 sec
Bids side by side The plumber's and electrician's quotes side by side, with the lowest flagged and carried. 42 sec

Coming soon Ask your estimate anything. Claude first, ChatGPT to follow. See how it will work

Questions

Can I show what the kitchen comes to on its own?

Yes. Tag each line with an area and group the sheet by it. Every room gets its own subtotal.

Can I give the client a price with and without an upgrade?

Yes. Switch the upgrade's line off. It stays on the sheet, struck through, with what it comes to shown beside the totals, and the tender total leaves it out. Switch it back on to see the total with it. The amount beside the totals is its cost, before contingency, fee, bond and insurance.

Can I price soft strip by the square metre?

Yes. Units are free text, so m², m and nr all work. Bidfident doesn't convert between units, so price each line in the unit its rate is in.

Can I carry skips and supervision as prelims?

Yes. On the Overhead tab, price skip exchanges by number and supervision by the week. Weekly items can follow the job duration, so they update when the programme changes.

Can I hand the homeowner a finished kitchen quote from Bidfident?

Not yet. The Client view hides your hours and rates on screen, but its unit prices are your cost, before markups. The Bid summary gives you the total for the kitchen quote you send.

Can I measure up the kitchen on a tablet at the client's house and price it there?

Not yet. Editing an estimate on a phone or tablet isn't built, so take your measurements back and price the refurb on a computer.

Does Bidfident work with Claude or ChatGPT?

Not yet, but it's coming. You'll be able to connect Bidfident to your own Claude or ChatGPT account and ask about your estimates in plain English. The answers will come from Bidfident's own figures, so they match the estimate. It will use the account you already have: Claude first, ChatGPT to follow.

Price your next refurbishment tender in Bidfident

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.