Bidfident for concrete contractors
Estimating software for concrete forming and finishing
Concrete contractors use Bidfident to price a slab line by line: edge forms by the linear foot, concrete by the cubic yard with a pump charged for its own hours, finish and curing by the square foot, and saw cuts by the foot. Carpenters, cement masons and laborers each take their own rate, rebar bids sit side by side, and cold weather protection goes in as a lump sum.
Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.
Sound familiar?
The pump priced for the whole job
The pump is on site for the pour, not for every hour the cement masons spend on the line. In Bidfident the pump on a line can have its own hours per unit, so it's charged for the time it runs.
Three crews, one rate
Carpenters forming, cement masons placing and laborers curing don't cost the same, but a blended rate treats them alike. In Bidfident each line takes its trade's rate from the library.
Rebar bids in your inbox
Rebar numbers come in by email, and the lowest isn't always the one carried. In Bidfident each sub's bids sit side by side, the lowest is flagged, and you carry the one you pick.
How Bidfident fits your work

The pump for its own hours
Give the pump on the concrete line its own hours per cubic yard and it's charged for that time. Leave it blank, as on the power trowel line, and it runs for the crew's hours.

Carpenters, cement masons and laborers
Forms at the carpenter's rate, placing and finishing at the cement mason's, curing at the laborer's. Each line takes its trade's rate from the library.

Cubic yards, square feet and linear feet
Concrete by the cubic yard, finish and curing by the square foot, forms and saw cuts by the linear foot. Each line takes a quantity, hours per unit, a material price with a waste percentage, and equipment by the hour.

Rebar bids side by side
Enter each bid for reinforcing steel, furnish and install, see the lowest flagged, and carry it or the one you pick. No number yet? Carry a plug.

Catch a slab line before it goes out
Lines to check flags a line with no quantity, no cost code, a total of zero, or hours or a material price more than 25% off the library's. Mark a line as right and it stays quiet.

Cold weather and the foreman
Insulated blankets and cold weather protection as a lump sum, and the foreman by the week, linked to the job duration.
Worked example: slab on grade for a warehouse addition
A made-up job, priced in Bidfident: 33 lines of your own work, 3 subs and 5 general conditions items over a 6-week job. The 5 lines this page talks about are listed one by one, and the rest are added up in one row. It's the same job you can open as an example project in Bidfident, so every figure below matches it.
To open this job in Bidfident: sign in and set up your company in the US, then on the Projects screen, under Example project, pick "Specialty contractors" and "Concrete" and press Add example project.
| Item | Amount |
|---|---|
Edge forms, slab on grade, 425 LF
| $5,091.50 |
Concrete, 4,000 psi, placed, 260 CY
| $56,849.00 |
Power trowel finish, 10,750 SF
| $4,316.13 |
Curing compound, 10,750 SF
| $1,343.75 |
Saw-cut control joints, 1,570 LF
| $2,072.40 |
28 more lines of your own work
| $195,156.33 |
| Item | Amount |
|---|---|
Reinforcing steel, furnish and install
| $27,400.00 |
Concrete testing, cylinders and slump
| $5,440.00 |
Joint filler at saw cuts, allowance
| $6,800.00 |
| Item | Amount |
|---|---|
Supervision, foreman
| $7,200.00 |
Cold weather protection, insulated blankets
| $3,400.00 |
Project manager, part time
| $2,880.00 |
Small tools, vibrators and consumables
| $1,152.00 |
Dumpsters and concrete washout
| $1,080.00 |
| Item | Amount |
|---|---|
Own work
| $264,829.11 |
| Excluded lines, not counted | $6,996.00 |
| Subcontractors | $39,640.00 |
General conditions
| $15,712.00 |
Direct cost
| $320,181.11 |
Contingency
| $12,807.24 |
Fee
| $33,298.84 |
| Subtotal before the bond | $366,287.19 |
Bond
| $3,662.87 |
Insurance
| $1,831.44 |
Bid total
| $371,781.50 |
See it in Bidfident
Coming soon Ask your estimate anything. Claude first, ChatGPT to follow. See how it will work
Questions
Can I price concrete by the cubic yard?
Yes. Units are free text, so CY, SF, LF and EA all work. Bidfident doesn't convert between units, so price each line in the unit its rate is in.
Can the pump be priced for less time than the crew?
Yes. Give the line's equipment its own hours per unit. Leave it blank and it runs for the crew's hours, as a power trowel usually does.
Can I add waste to the concrete?
Yes. Each line has a waste percentage on its material, so the concrete can carry 3% and the forms 10%.
Does it work out cubic yards from the slab size?
No. Bidfident doesn't calculate volumes from drawings or dimensions. Work out the cubic yards, then type or paste them in.
Can I price cold weather protection separately?
Yes. Add it to general conditions as a lump sum, by the week or by the month. Weekly and monthly items can follow the job duration.
What if the cement mason rate goes up after I bid the slab?
A submitted bid keeps the labor and equipment rates it was priced with, so a new cement mason or pump rate in your library doesn't move a number you've already turned in.
Does Bidfident work with Claude or ChatGPT?
Not yet, but it's coming. You'll be able to connect Bidfident to your own Claude or ChatGPT account and ask about your estimates in plain English. The answers will come from Bidfident's own figures, so they match the estimate. It will use the account you already have: Claude first, ChatGPT to follow.
Price your next concrete bid in Bidfident
Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.