Bidfident

Bidfident for underground utility contractors

Estimating software for underground utilities

For water, sewer and storm work, Bidfident prices pipe by the metre, trenching and bedding by the cubic metre, and manholes each. Pipelayers, operators and labourers each carry their own rate, the excavator gets its own hours on every line, camera inspection comes in as a subtrade, and the trench box and superintendent follow the schedule week by week.

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.

Sound familiar?

  • One excavator, very different hours

    Digging trench takes the excavator minutes per cubic metre, setting a manhole takes hours. A spreadsheet with one machine rate gets both wrong. In Bidfident each line gives the excavator its own hours per unit.

  • Pipelayers at a blended rate

    Pipelayers, operators and labourers end up at one average rate, and the price drifts as the crew mix changes. In Bidfident each line takes its trade's rate from the library, and any line can carry its own rate, marked in purple.

  • Trench box rental stuck at the old schedule

    The job grows from 7 weeks to 9, and the trench box and superintendent stay where they were. In Bidfident weekly items linked to the job duration follow it.

How Bidfident fits your work

  • Bidfident screenshot: pipe by the metre, manholes each

    Pipe by the metre, manholes each

    Sewer and watermain by the metre, trench and bedding by the cubic metre, manholes each. Each line has crew hours per unit and a material price with a waste percentage.

  • Bidfident screenshot: excavator hours line by line

    Excavator hours line by line

    The excavator can run 0.04 hours per cubic metre on trenching and 3 hours on each manhole. Each line charges it for its own hours, not the crew's.

  • Bidfident screenshot: pipelayers, operators and labourers

    Pipelayers, operators and labourers

    Set a rate for each trade once in the library. Every line takes its trade's rate, so a pipe line and a bedding line are each priced right.

  • Bidfident screenshot: trench box by the week

    Trench box by the week

    Rent the trench box and pay the superintendent by the week, linked to the job duration. Change the weeks and both follow.

  • Bidfident screenshot: camera inspection and testing bids

    Camera inspection and testing bids

    Enter each bid for sewer camera inspection or testing, see the lowest flagged, and carry it or the one you pick. Carry a plug amount until bids arrive.

  • Bidfident screenshot: group by street or phase

    Group by street or phase

    Tag lines with an area or location, like a street or a phase of the subdivision, and group the sheet with a subtotal for each.

Worked example: water and sewer services for a 24-lot subdivision phase

A made-up job, priced in Bidfident: 28 lines of your own work, 4 subtrades and 5 overhead items over a 7-week job. The 5 lines this page talks about are listed one by one, and the rest are added up in one row. It's the same job you can open as an example project in Bidfident, so every figure below matches it.

To open this job in Bidfident: sign in and set up your company in Canada, then on the Projects screen, under Example project, pick "Civil and site work" and "Underground utilities" and press Add example project.

Your own work
ItemAmount
Trench excavation and backfill, 1,200 m3
  • Labour: 1,200 m3 × 0.09 hrs = 108 hrs at $72.00/hr (equipment operator) = $7,776.00
  • Equipment: excavator, 30 t, 1,200 m3 × 0.04 hrs = 48 hrs, less than the crew, at $195.00/hr = $9,360.00
$17,136.00
PVC sanitary sewer, 200 mm, 360 m
  • Labour: 360 m × 0.35 hrs = 126 hrs at $66.00/hr (pipelayer) = $8,316.00
  • Material: 360 m × $42.00 + 3% waste = $15,573.60
$23,889.60
PVC watermain, 150 mm, 340 m
  • Labour: 340 m × 0.3 hrs = 102 hrs at $66.00/hr (pipelayer) = $6,732.00
  • Material: 340 m × $36.00 + 3% waste = $12,607.20
$19,339.20
Precast manholes, 1200 mm, 5 ea
  • Labour: 5 ea × 10 hrs = 50 hrs at $66.00/hr (pipelayer) = $3,300.00
  • Material: 5 ea × $4,200.00 = $21,000.00
  • Equipment: excavator, 30 t, 5 ea × 3 hrs = 15 hrs, less than the crew, at $195.00/hr = $2,925.00
$27,225.00
Pipe bedding, clear stone, 270 m3
  • Labour: 270 m3 × 0.1 hrs = 27 hrs at $52.00/hr (labourer) = $1,404.00
  • Material: 270 m3 × $34.00 + 10% waste = $10,098.00
$11,502.00
23 more lines of your own work
  • Labour $59,787.40 + material $153,902.70 + equipment $33,943.50
  • 1 more line is priced but left out of the total
$247,633.60
Subtrades
ItemAmount
Camera inspection of the sewer
  • Bids: Bidder A $5,400.00, Bidder B $4,950.00
  • Carrying the lowest: Bidder B
$4,950.00
Asphalt patching at tie-ins
  • Bids: Bidder A $7,800.00, Bidder B $8,400.00, Bidder C $7,200.00
  • Carrying the picked bid: Bidder A
$7,800.00
Survey layout and as-built drawings
  • Bids: Bidder A $6,900.00, Bidder B $7,400.00
  • Carrying the lowest: Bidder A
$6,900.00
Rock and boulder removal, allowance
  • No bids yet: carrying the plug amount
$9,000.00
Overhead
ItemAmount
Site superintendent
  • 7 wk × $2,900.00, following the job duration
$20,300.00
Trench box rental
  • 7 wk × $850.00, following the job duration
$5,950.00
Mobilize excavator, backhoe and trench box
  • 1 LS × $7,500.00
$7,500.00
Traffic control at the tie-ins
  • 6 day × $1,200.00
$7,200.00
Site trailer
  • 7 wk × $260.00, following the job duration
$1,820.00
Bid summary
ItemAmount
Own work
  • Labour $87,315.40 + material $213,181.50 + equipment $46,228.50
$346,725.40
Excluded lines, not counted$7,425.60
Subtrades$28,650.00
Overhead
  • 7 weeks
$42,770.00
Direct cost
  • Own work + subtrades + overhead
$418,145.40
Contingency
  • 4% of direct cost
$16,725.82
Fee
  • 10% of direct cost plus contingency
$43,487.12
Subtotal before bonding$478,358.34
Bonding
  • 1% of the subtotal
$4,783.58
Insurance
  • 0.5% of the subtotal
$2,391.79
Bid total
  • The price you submit, before GST
$485,533.71
GST, for reference
  • 5%, shown separately and not part of the bid total
$24,276.69

See it in Bidfident

Labour by trade Pipelayers, operators and labourers each take their own rate from the library, line by line. 33 sec
Site costs that follow the schedule The trench box and superintendent by the week follow the job duration as it changes. 38 sec
Group by area or floor Water and sewer work grouped by street, with a subtotal for each. 34 sec

Coming soon Ask your estimate anything. Claude first, ChatGPT to follow. See how it will work

Questions

Can I price pipe by the metre and manholes each?

Yes. Units are free text, so m, m³ and ea work side by side. Bidfident doesn't convert between units.

Can a manhole line use more excavator time than a trench line?

Yes. Every line gives the excavator its own hours per unit, so each one is charged for the time it needs.

Can pipelayers have a different rate from operators?

Yes. Set a rate for each trade in the library. Any single line can also carry its own rate.

Can the trench box follow the schedule?

Yes. Add it by the week and link it to the job duration, and it updates when the duration changes.

Can I split the job by street or phase?

Yes. Tag lines with an area or location and group the sheet by it, with subtotals. The cost report can filter by them too.

Can it track pipe laid against the estimate?

No. Bidfident is for pricing the job. It doesn't do job costing against actuals or time tracking.

Does Bidfident work with Claude or ChatGPT?

Not yet, but it's coming. You'll be able to connect Bidfident to your own Claude or ChatGPT account and ask about your estimates in plain English. The answers will come from Bidfident's own figures, so they match the estimate. It will use the account you already have: Claude first, ChatGPT to follow.

Price your next underground bid in Bidfident

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.