Bidfident

Bidfident for drainage contractors

Estimating software for drainage and utilities

For drainage and water mains, Bidfident prices pipe by the metre, trench dig and bedding by the cubic metre, and manholes by number. Pipelayers, plant operators and groundworkers each carry their own rate, the excavator gets its own hours on every line, the CCTV survey comes in as a subcontract package, and trench box hire and the site manager follow the programme week by week.

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.

Sound familiar?

  • One excavator, very different hours

    Digging trench takes the excavator minutes per cubic metre, setting a manhole takes hours. A spreadsheet with one plant rate gets both wrong. In Bidfident each line gives the excavator its own hours per unit.

  • Pipelayers at a blended rate

    Pipelayers, plant operators and groundworkers end up at one average rate, and the price drifts as the gang changes. In Bidfident each line takes its trade's rate from the library, and any line can carry its own rate, marked in purple.

  • Trench box hire stuck at the old programme

    The job grows from 7 weeks to 9, and the trench box and site manager stay where they were. In Bidfident weekly items linked to the job duration follow it.

How Bidfident fits your work

  • Bidfident screenshot: pipe by the metre, manholes by number

    Pipe by the metre, manholes by number

    Foul sewer and water main by the metre, trench and bedding by the cubic metre, manholes as nr. Each line has labour hours per unit and a materials price with a waste percentage.

  • Bidfident screenshot: excavator hours line by line

    Excavator hours line by line

    The excavator can work 0.04 hours per cubic metre on trenching and 3 hours on each manhole. Each line charges it for its own hours, not the gang's.

  • Bidfident screenshot: pipelayers, plant operators and groundworkers

    Pipelayers, plant operators and groundworkers

    Set a rate for each trade once in the library. Every line takes its trade's rate, so a pipe line and a bedding line are each priced right.

  • Bidfident screenshot: trench box hire by the week

    Trench box hire by the week

    Hire the trench box and pay the site manager by the week, linked to the job duration. Change the weeks and both follow.

  • Bidfident screenshot: cCTV survey and testing quotes

    CCTV survey and testing quotes

    Enter each quote for the CCTV survey or pressure testing, see the lowest flagged, and carry it or the one you choose. Carry an allowance until quotes arrive.

  • Bidfident screenshot: group by road or phase

    Group by road or phase

    Tag lines with an area or location, like a road or a phase of the development, and group the sheet with a subtotal for each.

Worked example: drainage and water mains for a 24-plot housing phase

A made-up job, priced in Bidfident: 28 lines of your own work, 4 subcontract packages and 5 preliminaries items over a 7-week programme. The 5 lines this page talks about are listed one by one, and the rest are added up in one row. It's the same job you can open as an example project in Bidfident, so every figure below matches it.

To open this job in Bidfident: sign in and set up your company in the UK, then on the Projects screen, under Example project, pick "Civils and groundworks" and "Drainage and utilities" and press Add example project.

Your own work
ItemAmount
Trench excavation and backfill, 1,200 m3
  • Labour: 1,200 m3 × 0.09 hrs = 108 hrs at £30.00/hr (plant operator) = £3,240.00
  • Plant: excavator, 30 t (360), 1,200 m3 × 0.04 hrs = 48 hrs, less than the crew, at £75.00/hr = £3,600.00
£6,840.00
PVC-U foul sewer, 200 mm, 360 m
  • Labour: 360 m × 0.35 hrs = 126 hrs at £29.00/hr (pipelayer) = £3,654.00
  • Materials: 360 m × £22.00 + 3% waste = £8,157.60
£11,811.60
PE water main, 150 mm, 340 m
  • Labour: 340 m × 0.3 hrs = 102 hrs at £29.00/hr (pipelayer) = £2,958.00
  • Materials: 340 m × £26.00 + 3% waste = £9,105.20
£12,063.20
Precast concrete manholes, 1200 mm rings, 5 nr
  • Labour: 5 nr × 10 hrs = 50 hrs at £29.00/hr (pipelayer) = £1,450.00
  • Materials: 5 nr × £2,400.00 = £12,000.00
  • Plant: excavator, 30 t (360), 5 nr × 3 hrs = 15 hrs, less than the crew, at £75.00/hr = £1,125.00
£14,575.00
Pipe bedding and surround, 20 mm gravel, 270 m3
  • Labour: 270 m3 × 0.1 hrs = 27 hrs at £28.00/hr (groundworker) = £756.00
  • Materials: 270 m3 × £42.00 + 10% waste = £12,474.00
£13,230.00
23 more lines of your own work
  • Labour £26,864.10 + materials £78,296.95 + plant £13,149.90
  • 1 more line is priced but left out of the total
£118,310.95
Subcontractors
ItemAmount
CCTV survey of the sewer
  • Quotes: Bidder A £2,900.00, Bidder B £2,650.00
  • Carrying the lowest: Bidder B
£2,650.00
Carriageway reinstatement at connections
  • Quotes: Bidder A £4,290.00, Bidder B £4,620.00, Bidder C £3,960.00
  • Carrying the chosen quote: Bidder A
£4,290.00
Setting out and as-built survey
  • Quotes: Bidder A £3,795.00, Bidder B £4,070.00
  • Carrying the lowest: Bidder A
£3,795.00
Rock and boulder breaking, allowance
  • No quotes yet: carrying an allowance
£5,000.00
Preliminaries
ItemAmount
Site manager
  • 7 wk × £1,600.00, following the programme
£11,200.00
Trench box hire
  • 7 wk × £450.00, following the programme
£3,150.00
Mobilise excavator, backhoe and trench box
  • 1 LS × £4,000.00
£4,000.00
Traffic management at the connections
  • 6 day × £650.00
£3,900.00
Site cabin
  • 7 wk × £150.00, following the programme
£1,050.00
Tender summary
ItemAmount
Own work
  • Labour £38,922.10 + materials £120,033.75 + plant £17,874.90
£176,830.75
Excluded lines, not counted£4,695.40
Subcontractors£15,735.00
Preliminaries
  • 7 weeks
£23,300.00
Direct cost
  • Own work + subcontractors + preliminaries
£215,865.75
Contingency
  • 4% of direct cost
£8,634.63
Overheads and profit
  • 10% of direct cost plus contingency
£22,450.04
Subtotal before the bond£246,950.42
Bond
  • 1% of the subtotal
£2,469.50
Insurance
  • 0.5% of the subtotal
£1,234.75
Tender total
  • The price you tender, before VAT
£250,654.67
VAT, for reference
  • 20%, shown separately and not part of the tender total
£50,130.93

See it in Bidfident

Labour by trade Pipelayers, plant operators and groundworkers each take their own rate from the library, line by line. 33 sec
Site costs that follow the schedule Trench box hire and the site manager by the week follow the programme as it changes. 38 sec
Group by area or floor Drainage and water main work grouped by road, with a subtotal for each. 34 sec

Coming soon Ask your estimate anything. Claude first, ChatGPT to follow. See how it will work

Questions

Can I price pipe by the metre and manholes by number?

Yes. Units are free text, so m, m³ and nr work side by side. Bidfident doesn't convert between units.

Can a manhole line use more excavator time than a trench line?

Yes. Every line gives the excavator its own hours per unit, so each one is charged for the time it needs.

Can pipelayers have a different rate from plant operators?

Yes. Set a rate for each trade in the library. Any single line can also carry its own rate.

Can trench box hire follow the programme?

Yes. Add it by the week and link it to the job duration, and it updates when the duration changes.

Can I split the job by road or phase?

Yes. Tag lines with an area or location and group the sheet by it, with subtotals. The cost report can filter by them too.

Can it track pipe laid against the estimate?

No. Bidfident is for pricing the job. It doesn't do job costing against actuals or time tracking.

Does Bidfident work with Claude or ChatGPT?

Not yet, but it's coming. You'll be able to connect Bidfident to your own Claude or ChatGPT account and ask about your estimates in plain English. The answers will come from Bidfident's own figures, so they match the estimate. It will use the account you already have: Claude first, ChatGPT to follow.

Price your next drainage tender in Bidfident

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.