Bidfident is built for estimators who price earthworks by the square metre and the cubic metre. Topsoil strip, cut and fill, trimming to formation, proof rolling and respreading each go on their own line, the dozer, motor grader and roller get their own hours apart from the operator's, setting out comes in as a subcontract package, and silt fencing sits in the prelims.

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.

Sound familiar?

  • Dozer and grader time lumped in with the gang

    Bulk earthworks and trimming use different machines for very different hours, but a spreadsheet row often has one blended rate. In Bidfident each line names its own plant with its own hours per unit, apart from the operator's.

  • Big areas, tiny rates

    On a 14,500 square metre playing field, a slip in hours per square metre moves the price by thousands. Bidfident keeps the running total in view and briefly shows how much it moved after each change, so a slip shows at once.

  • The same area on five lines

    Strip, trim, proof roll and respread all use the field's area, and when it changes some rows get missed. In Bidfident the sheet fills down like Excel, and every change is one undo step if you go too far.

How Bidfident fits your work

  • Bidfident screenshot: dozer, grader and roller for their own hours

    Dozer, grader and roller for their own hours

    A cut and fill line can carry the dozer at its own hours per cubic metre, and trimming the motor grader at its own hours per square metre. Each machine is charged for the time it works.

  • Bidfident screenshot: every pass on its own line

    Every pass on its own line

    Strip, cut and fill, trim to formation, proof roll and respread each get a line with a quantity, a unit, labour hours per unit and plant. Totals update as you type.

  • Bidfident screenshot: outputs kept in the library

    Outputs kept in the library

    Save tasks with their hours per unit, like trimming per square metre, in the company library. Every estimate picks up the same outputs.

  • Bidfident screenshot: setting out as a subcontract package

    Setting out as a subcontract package

    Enter each engineer's price for setting out and level checks side by side, see the lowest flagged, and carry it or another you choose.

  • Bidfident screenshot: group by pitch, car park or access road

    Group by pitch, car park or access road

    Tag lines with an area, like the main pitch, the car park or the access road, and group the sheet with a subtotal for each.

  • Bidfident screenshot: silt fencing and supervision in the prelims

    Silt fencing and supervision in the prelims

    Silt fencing as a lump sum, the site manager by the week. Linked weekly items follow the programme, even part weeks like 4.5.

Worked example: earthworks and levels for a school playing field

A made-up job, priced in Bidfident: 27 lines of your own work, 3 subcontract packages and 5 preliminaries items over a 5-week programme. The 5 lines this page talks about are listed one by one, and the rest are added up in one row. It's the same job you can open as an example project in Bidfident, so every figure below matches it.

To open this job in Bidfident: sign in and set up your company in the UK, then on the Projects screen, under Example project, pick "Civils and groundworks" and "Earthworks" and press Add example project.

Your own work
ItemAmount
Strip and stockpile topsoil, 14,500 m2
  • Labour: 14,500 m2 × 0.008 hrs = 116 hrs at £30.00/hr (plant operator) = £3,480.00
  • Plant: dozer, d6 class, 14,500 m2 × 0.005 hrs = 72.5 hrs, less than the crew, at £65.00/hr = £4,712.50
£8,192.50
Cut and fill on site, 6,200 m3
  • Labour: 6,200 m3 × 0.03 hrs = 186 hrs at £30.00/hr (plant operator) = £5,580.00
  • Plant: dozer, d6 class, 6,200 m3 × 0.018 hrs = 111.6 hrs, less than the crew, at £65.00/hr = £7,254.00
£12,834.00
Trim to formation, plus or minus 25 mm, 14,500 m2
  • Labour: 14,500 m2 × 0.006 hrs = 87 hrs at £30.00/hr (plant operator) = £2,610.00
  • Plant: motor grader, 14,500 m2 × 0.004 hrs = 58 hrs, less than the crew, at £75.00/hr = £4,350.00
£6,960.00
Formation compaction and proof roll, 14,500 m2
  • Labour: 14,500 m2 × 0.004 hrs = 58 hrs at £28.00/hr (groundworker) = £1,624.00
  • Plant: single drum roller, 7 t, 14,500 m2 × 0.003 hrs = 43.5 hrs, less than the crew, at £25.00/hr = £1,087.50
£2,711.50
Respread topsoil, 150 mm, 14,500 m2
  • Labour: 14,500 m2 × 0.007 hrs = 101.5 hrs at £30.00/hr (plant operator) = £3,045.00
  • Plant: dozer, d6 class, 14,500 m2 × 0.005 hrs = 72.5 hrs, less than the crew, at £65.00/hr = £4,712.50
£7,757.50
22 more lines of your own work
  • Labour £19,111.80 + materials £28,100.25 + plant £13,765.50
  • 1 more line is priced but left out of the total
£60,977.55
Subcontractors
ItemAmount
Setting out and level checks
  • Quotes: Bidder A £4,800.00, Bidder B £4,200.00
  • Carrying the lowest: Bidder B
£4,200.00
Compaction and plate bearing testing
  • Quotes: Bidder A £3,400.00, Bidder B £3,150.00
  • Carrying the lowest: Bidder B
£3,150.00
Imported topsoil if the site stock runs short, allowance
  • No quotes yet: carrying an allowance
£6,500.00
Preliminaries
ItemAmount
Site manager
  • 5 wk × £1,600.00, following the programme
£8,000.00
Silt fencing and pollution control
  • 1 LS × £2,600.00
£2,600.00
Mobilise and demobilise plant
  • 1 LS × £3,800.00
£3,800.00
Site cabin and welfare unit, serviced
  • 5 wk × £265.00, following the programme
£1,325.00
Road sweeper and dust suppression
  • 10 day × £420.00
£4,200.00
Tender summary
ItemAmount
Own work
  • Labour £35,450.80 + materials £28,100.25 + plant £35,882.00
£99,433.05
Excluded lines, not counted£45,298.00
Subcontractors£13,850.00
Preliminaries
  • 5 weeks
£19,925.00
Direct cost
  • Own work + subcontractors + preliminaries
£133,208.05
Contingency
  • 3% of direct cost
£3,996.24
Overheads and profit
  • 10% of direct cost plus contingency
£13,720.43
Subtotal before the bond£150,924.72
Bond
  • 1% of the subtotal
£1,509.25
Insurance
  • 0.5% of the subtotal
£754.62
Tender total
  • The price you tender, before VAT
£153,188.59
VAT, for reference
  • 20%, shown separately and not part of the tender total
£30,637.72

See it in Bidfident

Equipment that runs less than the crew The dozer and grader each get their own hours per unit, so plant time follows the work. 30 sec
The bid, always in view Change an earthworks output and the total shows how much it moved, straight away. 36 sec
One library for every estimate Earthworks outputs, plant and trades in one library, used by every estimate. 42 sec

Coming soon Ask your estimate anything. Claude first, ChatGPT to follow. See how it will work

Questions

Can the dozer and grader work fewer hours than the operator?

Yes. Each line's plant can have its own hours per unit. Leave it blank and the machine works the gang's hours.

Can I keep my outputs per square metre?

Yes. Save them as tasks with hours per unit in the rate library, and pick them from the line picker by typing a description.

Does it work out cut and fill from a survey?

No. Bidfident doesn't read survey files, drawings or maps. Enter the volumes your survey or earthworks software gives you.

Can I price in hectares?

Units are free text, so any unit works. Bidfident doesn't convert between units, so price each line in the unit its rate is in.

Can silt fencing go in as a lump sum?

Yes. Add it as a preliminaries item by lump sum on the Overhead tab, beside weekly items like the site manager.

What if wet weather adds a week to the earthworks?

Change the job duration and the site manager, and every other weekly or monthly preliminaries item linked to it, updates. Part weeks are allowed.

Does Bidfident work with Claude or ChatGPT?

Not yet, but it's coming. You'll be able to connect Bidfident to your own Claude or ChatGPT account and ask about your estimates in plain English. The answers will come from Bidfident's own figures, so they match the estimate. It will use the account you already have: Claude first, ChatGPT to follow.

Price your next earthworks tender in Bidfident

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.