Hazardous materials work mixes square metres and single items on the same job. Price lead paint removal on steelwork by the m² with a vacuum blasting unit at its own hours, PCB capacitors and fluorescent tubes by the nr, and mould remediation by the m². Bidfident carries hazardous waste disposal as a subcontract, keeps air monitoring in step with the programme, and adds the bond and insurance on top.

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.

Sound familiar?

  • Lead, PCBs and mould on one sheet

    Each hazard has its own unit, gang hours and consumables, and a spreadsheet built for one gets bent to fit the rest. In Bidfident every line carries its own unit, hours per unit and material, and the cost report totals each cost code, so every hazard shows its own figure.

  • Counting fittings by the hundred

    Hundreds of capacitors and over a thousand tubes, priced by hand with a calculator beside the sheet. In Bidfident you type the count, the hours and the rate per item, and the line totals as you go.

  • Blasting plant over-charged

    The vacuum blasting unit doesn't run every hour the gang is on the steelwork, but a single row charges it as if it did. In Bidfident the unit gets its own hours per unit, apart from the gang's.

How Bidfident fits your work

  • Bidfident screenshot: a total for each hazard

    A total for each hazard

    The cost report totals lead paint, PCB capacitors, fluorescent tubes and mould by cost code under each division. Filter by area or cost type, and click a row to jump to it.

  • Bidfident screenshot: vacuum blasting at its own hours

    Vacuum blasting at its own hours

    Give the blasting unit its own hours per square metre of steelwork, so it's charged for the time it runs, not the gang's.

  • Bidfident screenshot: capacitors and tubes from your library

    Capacitors and tubes from your library

    Type a description and pick a task, material or assembly from your rate library, with its rate, to fill the line.

  • Bidfident screenshot: one rate library for every hazard

    One rate library for every hazard

    Keep operative rates, blasting plant, consumables and tasks with hours per unit in one company library. Every estimate uses it.

  • Bidfident screenshot: monitoring and supervision by the week

    Monitoring and supervision by the week

    Air monitoring and the removal supervisor by the week, linked to the job duration. A 4-week programme that becomes 5 picks up the extra week.

  • Bidfident screenshot: hazardous waste carriers compared

    Hazardous waste carriers compared

    Enter each waste carrier's quote for carriage and disposal, see the lowest flagged, and carry it or the one you pick.

Worked example: lead paint, PCB capacitors and mould at an empty warehouse

A made-up job, priced in Bidfident: 25 lines of your own work, 4 subcontract packages and 6 preliminaries items over a 4-week programme. The 4 lines this page talks about are listed one by one, and the rest are added up in one row. It's the same job you can open as an example project in Bidfident, so every figure below matches it.

To open this job in Bidfident: sign in and set up your company in the UK, then on the Projects screen, under Example project, pick "Demolition and asbestos removal" and "Hazardous materials" and press Add example project.

Your own work
ItemAmount
Lead paint removal, steel columns and beams, 920 m2
  • Labour: 920 m2 × 0.35 hrs = 322 hrs at £25.00/hr (specialist removal operative) = £8,050.00
  • Materials: 920 m2 × £3.00 = £2,760.00
  • Plant: vacuum blasting unit, 920 m2 × 0.1 hrs = 92 hrs, less than the crew, at £22.00/hr = £2,024.00
£12,834.00
Remove PCB capacitors from light fittings, 340 nr
  • Labour: 340 nr × 0.4 hrs = 136 hrs at £25.00/hr (specialist removal operative) = £3,400.00
  • Materials: 340 nr × £2.50 = £850.00
£4,250.00
Remove and package fluorescent tubes, 1,250 nr
  • Labour: 1,250 nr × 0.05 hrs = 62.5 hrs at £25.00/hr (specialist removal operative) = £1,562.50
  • Materials: 1,250 nr × £0.40 = £500.00
£2,062.50
Mould remediation, plasterboard and insulation, 180 m2
  • Labour: 180 m2 × 0.8 hrs = 144 hrs at £25.00/hr (specialist removal operative) = £3,600.00
  • Materials: 180 m2 × £6.00 = £1,080.00
£4,680.00
21 more lines of your own work
  • Labour £11,890.50 + materials £12,140.40 + plant £1,008.80
  • 1 more line is priced but left out of the total
£25,039.70
Subcontractors
ItemAmount
Hazardous waste carriage and disposal
  • Quotes: Bidder A £7,200.00, Bidder B £6,600.00
  • Carrying the lowest: Bidder B
£6,600.00
Lead and PCB wipe sampling, laboratory analysis
  • Quotes: Bidder A £2,640.00, Bidder B £2,860.00
  • Carrying the lowest: Bidder A
£2,640.00
Scaffolding for blast containment
  • Quotes: Bidder A £3,410.00, Bidder B £3,190.00
  • Carrying the lowest: Bidder B
£3,190.00
PCB sealant to window frames, allowance
  • No quotes yet: carrying an allowance
£1,900.00
Preliminaries
ItemAmount
Supervision, removal supervisor
  • 4 wk × £1,100.00, following the programme
£4,400.00
Air monitoring, independent analyst
  • 4 wk × £1,600.00, following the programme
£6,400.00
Site cabin and secure waste store
  • 4 wk × £143.00, following the programme
£572.00
Face-fit tests and blood lead tests
  • 6 ea × £116.00
£696.00
Method statements and hazardous waste registration
  • 1 LS × £358.00
£358.00
Mobilisation and demobilisation
  • 1 LS × £1,320.00
£1,320.00
Tender summary
ItemAmount
Own work
  • Labour £28,503.00 + materials £17,330.40 + plant £3,032.80
£48,866.20
Excluded lines, not counted£3,627.00
Subcontractors£14,330.00
Preliminaries
  • 4 weeks
£13,746.00
Direct cost
  • Own work + subcontractors + preliminaries
£76,942.20
Contingency
  • 6% of direct cost
£4,616.53
Overheads and profit
  • 12% of direct cost plus contingency
£9,787.05
Subtotal before the bond£91,345.78
Bond
  • 1.5% of the subtotal
£1,370.19
Insurance
  • 1% of the subtotal
£913.46
Tender total
  • The price you tender, before VAT
£93,629.43
VAT, for reference
  • 20%, shown separately and not part of the tender total
£18,725.89

See it in Bidfident

Totals by cost code Lead, PCB and mould work each totalled by cost code, with a filter by area or cost type. 39 sec
Search the rate library Type a description to find a capacitor, tube or mould task in your library, with its rate. 32 sec
One library for every estimate Operative rates, blasting plant, consumables and tasks kept once for the whole company. 42 sec

Coming soon Ask your estimate anything. Claude first, ChatGPT to follow. See how it will work

Questions

Can I price capacitors and tubes by the item?

Yes. Use nr as the unit, with hours and a rate per item. Units are free text.

Can lead paint, PCBs and mould have their own cost codes?

Yes. Start from cost codes named after the NRM2 work sections, or paste your own list, such as CESMM, in from Excel or QuickBooks with a preview first.

Can I see what each hazard costs on its own?

Yes. The cost report totals each cost code under its division, and you can copy the whole estimate by cost code as CSV.

Can I price mould remediation as an option?

Yes. Switch the line off as an alternate. It stays on the sheet struck through, and its cost before markups is shown beside the totals, but it isn't in the tender.

Does it count fittings from the drawings?

No. Bidfident doesn't read quantities from drawings or plans. You enter the counts yourself.

If my operative rate goes up, does a tender I've sent change?

No. A submitted tender keeps the labour and plant rates it was priced with, so raising the operative or blasting unit rate in your library doesn't move a price you've already sent.

Does Bidfident work with Claude or ChatGPT?

Not yet, but it's coming. You'll be able to connect Bidfident to your own Claude or ChatGPT account and ask about your estimates in plain English. The answers will come from Bidfident's own figures, so they match the estimate. It will use the account you already have: Claude first, ChatGPT to follow.

Price your next hazardous materials tender in Bidfident

Get started

Enter your email and Bidfident sends you a sign-in link. New companies start with a starter rate library. Who runs Bidfident, and what it keeps about you.